For almost twenty years, Chile’s small distributed plants have expanded across distribution networks. Updated monitoring and control requirements are now increasing their operational visibility.
Under DS 1/2026 and the updated CNE technical standard for PMGD (NTCO) and the Technical Annex “Definición de Parámetros Técnicos y Operativos para el Envío de Datos al SITR” of the NTSyCS, plants with a power surplus of up to 9 MW connected to a distribution network must send real-time data to their distributor, accept remote control of their coupling breaker and, where required, report real-time data to the CEN through their distributor. The change affects 831 plants and around 3.8 GW, mostly solar parks with a median size of 3 MW.
It also comes at a delicate moment. DS 1/2026 ends the stabilized price advantage for new PMGD, while the deadline for standardising protection records is already 30 November 2026, with separate deadlines extending to 19 August 2027 for protection-setting updates. For distributor monitoring and control, PMGD requiring equipment adaptations have one year from their distributor’s communication of its technical requirements, under Article 10-3 of the NTCO PMGD.
What PMGD owners need to do
The plant side of the chain is the owner’s responsibility: suitable control equipment for the coupling recloser, an RTU or gateway where needed to collect signals, GPS-based time synchronisation for SITR data and fault records, cybersecurity and a permanent telecom link.
Data must reach the CEN with at least 99.5% monthly availability, and a loss of monitoring and control signals can lead the distributor to disconnect the plant if it could compromise the safe operation of the distribution network.
Each distributor defines its own technical requirements within the limits established by the NTCO. CGE, for example, asks for the DNP3 protocol, a list of 150 signals and an MPLS link with Entel or Telefónica only, adding another layer of technical and cost considerations for plant owners.
Several questions are still open
Owners have started to ask for clarity. In its reply of 3 November 2026, the CEN confirmed that an exclusive MPLS link is not a SITR requirement, but referred fees, standards and liability for disconnections to distributors, the SEC and the CNE.
The Italian CCI roll-out offers a useful comparison: with the Controllore Centrale di Impianto (CCI), it was the regulator, not each distributor, that set protocol, timing and economics for medium-voltage plants.
Protections, fault recording, distributor monitoring and SITR reporting can share the devices and links: planning them together, in one architecture, avoids paying twice for the same assets and helps owners approach compliance as one integrated project.
How Vector Renewables supports PMGD owners
Our team in Chile can support PMGD owners throughout the compliance journey, from the first assessment to day-to-day operation:
- Portfolio screening
A gap analysis of each plant by distributor, recloser, RTU, GPS and telecom coverage, turned into a clear compliance roadmap against the 2026 and 2027 deadlines. - Owner’s engineering
Technical specification, integrator tender and quote benchmark, design review and commissioning with the distributor and the CEN. - Dialogue with distributors and authorities
Technical files to request justifications and cost breakdowns from distributors, and to bring open points to the SEC and the CNE, together with the owner’s legal advisors. - Availability monitoring with NUO
Our asset-management platform, NUO, keeps an independent record of link and data availability against the 99.5% target, providing owners with evidence in the event of a dispute with the distributor.
Behind the local team is Vector’s experience from the CCI roll-out in Italy, allowing lessons learned from a similar transition to be applied ahead of the Chilean deadlines.
Has your distributor already sent its SCADA and SITR requirements for your PMGD?
Talk to our team in Chile and find out what the new requirements mean for your plants, and what you need to do before the first deadlines.
> Book a PMGD compliance check
“Complying with Chile’s new PMGD requirements means testing remote operation of the coupling breaker and verifying that the required SITR signals reach the CEN reliably. It also means asking where each party’s responsibility begins and ends, who acts when a signal is lost, and how each distributor requirement aligns with the applicable technical standards.”